Kitchen planning
How Long Does a Kitchen Remodel Take?

How long does a kitchen remodel take? HomeAdvisor puts construction at 6 to 10 weeks after about 4 weeks of planning. Homeowners in the 2026 Houzz and Home Study reported longer projects: 9.5 months of planning and 5.8 months of construction on average.
The Phases, in Order
Step 1Design and quotes
About 4 weeks (HomeAdvisor)
Measure, settle the layout and get at least three written quotes for the same scope.
- Step 2
Ordering
Custom cabinets: 6 to 12 weeks to build (Fixr)
Cabinets drive the lead time. Ask your supplier for a ship date before you book demolition.
- Step 3
Permits
Needed when plumbing, wiring, ventilation or walls change; cabinet and countertop swaps are finish work under the model code (Springville City, Utah, Community Development, Work Exempt From Permits, 2021 IRC (2025-07-21 (file revision date))). Your city sets the timeline.
- Step 4
Demolition
Old cabinets, counters and flooring come out.
- Step 5
Rough-in and inspection
New plumbing and wiring go in and are inspected before walls close (City of Benson, Arizona, Work not requiring a Permit, according to the 2024 IRC (undated handout quoting the 2024 IRC)).
Step 6Walls, floors and cabinets
Drywall, flooring and cabinet installation.
- Step 7
Countertops
2 to 3 weeks from template to install for granite (Fixr); install takes about a day (HomeAdvisor)
The fabricator templates the installed cabinets, cuts the slab, then installs.
- Step 8
Finish and final inspection
Backsplash, fixtures, appliances, punch list and the final inspection.
What Makes It Take Longer
Custom cabinets, moving walls or plumbing, damage found behind walls, inspection backlogs and changes after work starts. In the 2026 Houzz and Home Study, 37% of renovating homeowners went over budget, and 22% of those blamed unexpected construction issues (Houzz Inc., 2026 U.S. Houzz & Home Study: Renovation Trends (covers renovations done in 2025) (2026 (survey fielded January to March 2026; report covered by the Composite Panel Association on 2026-05-14))). Surprises cost time as well as money.
How to Keep It on Schedule
- Order cabinets before demolition and confirm the ship date in writing.
- Approve every selection, down to the faucet and grout color, before work starts.
- Put the schedule and the change-order process in the contract.
Kitchen Remodel Permits Stayed Open a Median 157 to 218 Days in Austin, Seattle and Los Angeles
Building permits for one- and two-family homes whose description names a kitchen remodel, issued in 2023 or 2024, stayed open a median of 192 days from issue to final inspection in Austin (City of Austin permit data), 218 days in Seattle (Seattle SDCI permit data) and 157 days in Los Angeles (Los Angeles LADBS permit data), according to KBR’s analysis of those three city permit files. Within 180 days of issue, 40.2% of the Austin kitchen permits had reached final, 23.1% in Seattle and 39.7% in Los Angeles, by the same records.
This is permit open time (issue to final inspection), not build duration: the clock includes waits for inspections, permits left open after the work ended and stalled jobs. It counts only permits that reached final. By the 2026-11-25 data pull, 83.8% of the Austin kitchen permits had reached final, 78.0% in Seattle and 70.5% in Los Angeles (City of Austin, Seattle SDCI and Los Angeles LADBS permit records); the rest were still open, expired or withdrawn. Getting a remodel permit issued is a separate step: across 13 cities’ records, the median city took 14.5 days from application to issue, according to KBR’s permit wait analysis.
| City | Permits issued 2023 to 2024 | Reached final | Median days, issue to final | Middle half (25th to 75th percentile) |
|---|---|---|---|---|
| Austin | 234 | 196 (83.8%) | 192 | 130 to 296 days |
| Seattle | 91 | 71 (78.0%) | 218 | 168 to 359 days |
| Los Angeles | 3,976 | 2,804 (70.5%) | 157 | 90 to 274 days |
Filter: building permits for one- and two-family homes (Austin residential classes 434 and 435, Seattle single family or duplex alterations, Los Angeles alter or repair permits for 1 or 2 family dwellings) issued 2023-01-01 to 2024-12-31, with the word kitchen within four words of remodel, renovate, alteration, upgrade, update, reconfigure or a similar word. Additions, new or added rooms, ADU and garage conversions and supplemental permits are excluded. Final date: Austin completed date, Seattle completed date (all inspections done), Los Angeles status date of Permit Finaled. Chicago’s permit file was checked and has no final-inspection date. Sources: City of Austin permit data, Seattle SDCI permit data, Los Angeles LADBS permit data.
Living Through It
Set up a temporary kitchen in another room with a microwave, a kettle and a folding table. Plan for days without water or power to the kitchen during rough-in.
Frequently Asked Questions
How long does a kitchen remodel take?
6 to 10 weeks of construction plus about 4 weeks of planning, according to HomeAdvisor (HomeAdvisor (Angi Inc.), How Much Does It Cost to Remodel a Kitchen? (Updated 2026-06-17)).
What takes the longest in a kitchen remodel?
Usually cabinets. Custom cabinets take 6 to 12 weeks to build (Fixr, Kitchen Cabinet Installation Cost (Updated 2026-01-22)).
How long after cabinets are installed do countertops go in?
For granite, about 2 to 3 weeks from template to install (Fixr, Granite Countertop Installation Cost (Updated 2025-01-31)).
Can I stay in the house during a kitchen remodel?
Most people do. Set up a temporary kitchen and expect some days without water to the sink.
Next: Kitchen remodel cost calculator · Cabinet refacing vs replacing · How to choose a remodeling contractor
Sources
- HomeAdvisor (Angi Inc.), How Much Does It Cost to Remodel a Kitchen? (Updated 2026-06-17)
- City of Austin, Development Services Department, Issued Construction Permits (dataset 3syk-w9eu) (2015-07-09)
- City of Seattle, Seattle Department of Construction and Inspections, Building Permits (dataset 76t5-zqzr) (2017-07-06)
- City of Los Angeles, Department of Building and Safety, Building and Safety – Building Permits Issued from 2020 to Present (N) (dataset pi9x-tg5x) (2023-03-22)
- Houzz Inc., 2026 U.S. Houzz & Home Study: Renovation Trends (covers renovations done in 2025) (2026 (survey fielded January to March 2026; report covered by the Composite Panel Association on 2026-05-14))
- Fixr, Kitchen Cabinet Installation Cost (Updated 2026-01-22)
- Fixr, Granite Countertop Installation Cost (Updated 2025-01-31)
- HomeAdvisor (Angi Inc.), How Much Does It Cost to Install Granite Countertops? (Updated 2026-06-20)
- Springville City, Utah, Community Development, Work Exempt From Permits, 2021 IRC (2025-07-21 (file revision date))
- City of Benson, Arizona, Work not requiring a Permit, according to the 2024 IRC (undated handout quoting the 2024 IRC)